Creating, Editing, or Deleting a Structure
A structure usually consists of several hierarchical levels. The upper levels are nodes; the lowest level contains the objects that are assigned to a node.
Nodes can contain either more nodes or object assignments. If you have already assigned objects to a node, you cannot create another node under this node.
You can also delete a node directly from a structure. All subordinate nodes and objects assignments will be deleted automatically. This has no effect on the objects themselves.
Creating a new structure
To create a custom structure for a building model
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Go to the Multimodel manager palette, click
Options to the right of the Select structure list box and select
New structure.
You can see the Create structure dialog box.
-
Specify the Name and Type for the new structure. Then click CREATE.
This creates the structure with the topmost node.
-
Add more nodes to the structure and assign objects as described in the following section.
Adding nodes
To add a node to a structure
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Go to the Multimodel manager palette and expand the structure as far as the node under which you want to create another node.
Note: If the topmost node is the only one (for example, in a new structure), use this node for the next step. -
Open the
Context menu for this node and click
Create node.
You can see the Create node dialog box.
Important!
If you have already assigned objects to a node, you cannot create another node under this node. -
Specify the Name and Type for the new node. Then click CREATE.
This creates the node.
-
Complete the structure by repeating steps 1 to 3.
Right-click the node under which you want to create another node.
Adding further information to nodes
To add a comment, attachment, or hyperlink to a node
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Click the node in the Multimodel manager palette.
The Details palette opens on the right side.
-
If you want to add a comment, go to the Details palette, click
Comments, enter the comment in the box and click ADD COMMENT.
Or:
If you want to add an attachment, go to the Details palette, click
Attachments and then click ADD ATTACHMENT. Select the file in the Open dialog box and click Open.
Or:
If you want to add a hyperlink, go to the Details palette, click
Hyperlinks, enter the name and URL of the link, and click ADD HYPERLINK.
Renaming nodes
To rename a node
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Go to the Multimodel manager palette, open the
Context menu for the required node and click
Rename.
You can see the Rename node dialog box.
-
Enter the new name and click RENAME.
Moving nodes
To move a node
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Go to the Multimodel manager palette and point to the node that you want to move. All objects assigned to this node will be moved too.
-
Drag this node to its new position within the structure.
Deleting nodes
To delete a node
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Go to the Multimodel manager palette, open the
Context menu for the required node and click
Delete.
This deletes the node including all subordinate nodes and object assignments.
Note: The objects themselves will not be deleted!
Renaming a structure
To rename a structure
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Go to the Multimodel manager palette and select the required structure in the Select structure list box.
-
Click
Options to the right of the Select structure list box and select
Rename structure.
You can see the Rename structure dialog box.
-
Enter the new name and click RENAME.
Deleting a structure
To delete a structure
→ Multimodel manager is open (see “Opening the multimodel manager”)
→ You have the required rights (see “Rights in Bimplus”)
-
Go to the Multimodel manager palette and select the required structure in the Select structure list box.
-
Click
Options to the right of the Select structure list box and select
Delete structure.
-
Click DELETE to confirm the prompt.
This deletes the structure including all subordinate nodes and object assignments.
Note: The objects themselves will not be deleted!